Day 41 - ESE view from the screened porch.
|
SketchUp model showing art wall, kitchen island, and door to grilling balcony (center of image); see framing in photo below. |
Day 41 - The "blue art wall" that rises into the clerestory is fully framed. Clerestory def: an outside wall of a room or building that rises above an adjoining roof and contains windows.
|
Day 37 and Day 41 comparison (out of town for the Women's Final Four with just a touch of anxiety). As our friend Chet commented, "its simply because when you're there you know everything is going okay."
- - Very well put Chet! |
|
Days 36 - Stairwell and elevator openings trimmed out.
|
|
Days 36 and 37 - Final tweaks to the second floor (primary living space) framing before heading out of town. Speak now or forget it. |
|
Computer model image of large window in Master Bath. |
|
Day 36 - Master bath wall and large window framing being placed. |
|
Day 36 - Second floor framing begins in the afternoon. |
|
Day 35 - Second floor decking almost complete. |
It's is looking fantastic! I love the computer generated images, too, as I lack visual skills...lol. Can't wait to see more!
ReplyDelete